TriMark Executive Outlines Playbook for Smoother Menu-Driven Equipment Rollouts

Bryan Musgrove of TriMark USA recommends location-by-location playbooks, lead-time-based scheduling and consolidated packaging to help smooth equipment rollouts for new menu items.

Katarina VukovicNovember 1, 20265 min read3 views
A stainless-steel toaster, stacked smallwares, a holding cabinet and a site plan sit on a planning table, suggesting a restaurant equipment rollout being organized.

Adding a new menu item can require more than a recipe and a launch plan. Bryan Musgrove, divisional senior director on national accounts for TriMark USA, says restaurant operators also need a disciplined approach to rolling out the equipment that makes the item possible. He points to three practices: a location-specific playbook, a schedule tied to manufacturer lead times, and delivery packaging designed around each site.

Build a location-by-location playbook

Musgrove recommends creating a playbook that breaks down what every location will need. The goal is to separate sites that can accept new equipment with little or no modification from those that need extra work. In one rollout, TriMark worked with a brand adding toasted sandwiches to a breakfast lineup that already included biscuits and wraps. The brand needed new toasters, but not every site could accommodate them in the same way.

Musgrove notes that some locations already have their electrical capacity maxed out. Small mall or urban locations may also lack the counter space for a toaster. In those cases, an operator may have to create room by adding shelving or another table, a change that can affect workflow. A playbook gives the rollout team a clear view of which locations are plug-and-play and which require additional support.

Schedule from the manufacturer’s lead time

Equipment orders should be scheduled around how quickly the manufacturer can actually produce and deliver the units, not simply around the desired launch date. Musgrove uses a hypothetical order of 200 units to illustrate the issue. If a manufacturer can produce 10 units a week, the full order would take 20 weeks. A manufacturer might also have enough inventory for the first 50 units, then need to order parts from overseas, adding eight weeks before it can complete the rest.

For a menu item tied to a specific season or occasion, Musgrove says operators should work backward from the intended launch date. That makes it possible to build a timeline the manufacturer and the operator can meet. The schedule should reflect production capacity, parts availability and delivery, rather than assuming that all units will arrive as a single block.

Consolidate deliveries for each location

Packaging is another part of the rollout that can create unnecessary work at the store level. Instead of shipping smaller wares directly to locations in their original boxes, Musgrove suggests asking the dealer to consolidate and repackage them into one package per location. That approach can make deliveries easier for managers to receive and sort.

TriMark worked with one brand that added macaroni and cheese to its sides. The change required visual holding cabinets, pans and serving scoops in varying sizes. The items were combined into one package for each location, along with instructional materials and exterior labeling. The labeling let managers know exactly what they were receiving when the delivery arrived.

Planning before the menu launch

Musgrove’s recommendations address different points in the same process: deciding which locations need more support, timing production and delivery, and simplifying what arrives at the store. If the rollout goes as planned, the new menu item can generate attention and increase traffic. The underlying point is that equipment planning starts well before the item reaches the plate.